This is a logistically challenging project to provide refurbish the existing buildings and to construct a number of extensions to a live food processing facility.
To the front of the site, we are to construct an extension and carry out a full refurbishment of the offices, reception and laboratory areas. To the rear there are various extension to the production areas to accommodate further production area, storage and new cold store including new access doors and 4 new dock levellers.
Extensive external works are taking place, extending the rear yards to cope with the increased production from the site and incorporating a large attenuation system under these areas. To the front of the factory, the carparking has been extended and a further attenuation system has been installed.
All these works are being carried out whilst the site is live, and we are having to coordinate deliveries and collections to the site whilst constructing our works.
The project is progressing well with regular contractor/client meetings taking place to ensure production is unaffected by our contract works.